Give each change its own record
The International Construction Week 2026 review highlights traceability and data management among the BIM Forum topics. For a contractor, one practical application is tracking each change from request to financial impact. This guide proposes an operational workflow for extras and variations; approval and payment conditions must be checked against the contract for each project.
Preserve the baseline budget
Do not overwrite the initial budget whenever a new instruction arrives. Assign an identifier to the change and link the project, affected items, requester, reason and documents. Separate requested, priced, awaiting decision, approved, rejected and executed states. Forecasts may show pending changes as a scenario, but should not mix them with already accepted revenue or costs.
Assess cost, revenue and programme separately
Describe quantities and units, materials, subcontractors, hours and equipment needed. Identify the price proposed to the client and the contractor’s estimated cost: they are different figures. Add the impact on procurement, work sequence and committed dates. Record assumptions, exclusions and drawing revision. If a technical definition is missing, make that uncertainty visible before asking for a decision.
Illustrative example of an extra
On a fictional project, the client requests an extension to an enclosure. The proposed price is €8,000 and estimated cost €6,200, both excluding taxes: the forecast difference is €1,800 before other excluded costs. If the proposal is not accepted yet, that €8,000 is not approved revenue. The ERP should show the scenario and its status without silently changing the contractual baseline.
From approval to execution
Retain who approved, when, which version and under what conditions. Link subsequent orders and site records to the change identifier. If urgency requires work before the workflow is complete, record the exception and its owner; software does not turn an informal instruction into contractual acceptance. Later revisions should retain the history and reassess the remaining impact.
Close the change with evidence
Check that execution, actual cost, progress valuation and billing refer to the same scope. Review executed extras awaiting a decision, approved changes not passed to procurement and differences against the estimate each week. CADT can help connect this record with your ERP and project management. Bring an anonymised request, its estimate and an approval example to define the workflow and reports required.