Digitalisation starts with a fair comparison
IFEMA placed digitalisation among the themes of International Construction Week, held on 10–13 November 2026. One everyday application for procurement is comparing quotations with the same scope. This guide proposes a supplier comparison sheet to support decisions before issuing a purchase order; matching deliveries and invoices belongs to a later stage.
Define a common request
Identify the project, work item, specification, quantity, unit, unloading location and required date. Separate supply, transport, unloading equipment, installation and packaging removal where applicable. Ask suppliers to state exclusions, validity and conditions. Do not turn a missing price into zero: mark the item as awaiting clarification. Retain the original quotation and its revision.
Normalise units without hiding differences
A quotation per pallet and one per unit are comparable only when the conversion and accepted usable quantity are known. Document minimum order quantities, rounding to full packs and expected surplus. Keep one column for the original amount and another for the calculated comparable cost. If an alternative changes performance, obtain technical approval before treating it as an equivalent replacement.
Illustrative example of comparable cost
For 1,000 units, fictional quotation A charges €2 per unit plus €180 transport: €2,180. B charges €2.10 per unit including transport: €2,100. Excluding taxes and assuming identical scope, B is €80 lower. The conclusion changes if unloading is excluded or B requires purchasing 1,200 units. These figures illustrate the method; they are not market prices.
Assess timing and record the decision
Add confirmed availability, partial deliveries, access restrictions and payment terms. Do not confuse a commercial promise with an accepted delivery date for the site. Record the criteria supporting selection: comparable cost, technical compliance and fit with the programme. Urgency may justify another offer, but the reason should be explained and approved by the responsible person.
From comparison to the ERP purchase order
The order should inherit the awarded version, units, scope and project references. Preserve alternatives and approval rather than overwriting them when a revision arrives. CADT can review how requests, comparisons and orders connect in your construction software. Bring two anonymised quotations and a typical order to define the conversions and controls your team needs.